Update Overview:

As part of the 2035 Wake Transit Plan Update the Community Funding Area Program Management Plan (CFA PMP) was also reviewed for any needed updates. 

The last update to the Community Funding Area Program Management Plan (CFA PMP) was completed in 2020 as part of the 2030 Wake Trasnit Plan update process. It was a relatively minor update compared to the recommendations included in the draft 2025 CFAPMP. 

Development of the 2025 CFA PMP began in December 2023. The process has relied on active participation of TPAC members including CFA Program eligible participants.

Recommendations: 

  • Added Unincorporated Wake County as an Eligible area/applicant
  • Lowered Local Match Requirement from 50% to 35%
  • Removed funding cap on Planning/Technical Assistance Projects
  • Establish 3% Target for Planning funding each year
  • Projects still required to provide 35% Local Match
  • Increased overall funding for CFA Program
  • Tripled funding from $20M over next 10 years to $60M
  • All CFA project funding will come from this pot of money
  • Revised Scoring Criteria to account for new match requirement
  • Added appendix providing options to consider in future for graduation framework
  • Added clarification of process for scope and/or budget changes during Annual Review process

 

Project Development Team

Project Lead: Suvir Venkatesh (CAMPO)

CAMPO's Wake Transit staff are leading the development of the CFAPMP with inpiut and guidance from TPAC members including CFA Program participants.  

TPAC Member Agencies (Bold = FY26 CFA Eligible)

Apex            CAMPO              Fuquay-Varina

Cary             GoTriangle         Holly Springs     

Garner         Knighdale        Morrisville       

NCSU             Raleigh              Research Traingle

Rolesville     Wake County    Wake Forest         

Wendell        Zebulon

complete
complete
1st Draft Review Period

The draft CFA Program Management Plan will be published for an initial 30-day public review and comment period from May 1-31, 2025. Comments and feedback from transit partners and members of the community to help refine the draft for the final reivew period. 

live
live
2nd Draft Review Period

The final community review period will run from Sept 22-Oct 21, 2025. 

CAMPO will hold a public hearing for the draft CFAPMP at its Executive Board meeting on October 15, 2025.

Feedback recieved at the hearing and throughout this comment period will be collected, compiled and presented to the TPAC for review and application and will be presented to the Wake Transit governing boards before the CFAPMP is adopted. 

planned
planned
Adoption and Close Out

The Wake County Transit Planning Advisory Committee (TPAC) will review and recommend adoption of the CFAPMP to the Wake Transit governing boards on October 23rd.

The CAMPO and GoTriangle Boards will consider adoption at their respective meetings on November 20th.

The adopted plan will be published to the CAMPO Community Funding Area Program web page and the TPAC Document Library.

Recommendations in the adopted plan are expected to inform funding allocations included in the FY27 Wake Trasnit Work Plan.